A 174-foot, 950-ton section of the bridge was hoisted into place on Saturday. When finished, the bridge would have been 289 feet long and 109 feet tall.
The bridge was being built under what is called "accelerated bridge construction" methods, which are championed at FIU. The methods basically allow larger pieces to be fabricated away from traffic, rather than assembling lots of smaller pieces above a busy road.
"FIU is about building bridges and student safety. This project accomplishes our mission beautifully," FIU President Mark Rosenberg said after the Saturday installation.
vtsnowedin wrote:Yes this rapid construction process is all the rage and sometimes I think they throw in unreasonable requirements just so they can use the method and get an award or promotion. There is no glory in just putting in a temporary bridge and doing things the old fashioned way. Perhaps after this disaster they will rethink their enthusiasm for the method?
.
yellowcanoe wrote:vtsnowedin wrote:Yes this rapid construction process is all the rage and sometimes I think they throw in unreasonable requirements just so they can use the method and get an award or promotion. There is no glory in just putting in a temporary bridge and doing things the old fashioned way. Perhaps after this disaster they will rethink their enthusiasm for the method?
.
The old fashioned way involved rerouting traffic around the construction site for an extended period of time. Here in Ottawa a number of bridges on the expressway that runs through the center of the city have been replaced in recent years using a rapid bridge replacement procedure. New bridge sections (one for the east bound lanes and one for the west bound lanes) are built off site. Traffic needs to be rerouted for less than 72 hours on a long weekend in the summer to enable demolition of the old bridge sections and installation of the new bridge sections. This has worked well and is far more preferable to having many months of traffic disruption.
yellowcanoe wrote:vtsnowedin wrote:Yes this rapid construction process is all the rage and sometimes I think they throw in unreasonable requirements just so they can use the method and get an award or promotion. There is no glory in just putting in a temporary bridge and doing things the old fashioned way. Perhaps after this disaster they will rethink their enthusiasm for the method?
.
The old fashioned way involved rerouting traffic around the construction site for an extended period of time. Here in Ottawa a number of bridges on the expressway that runs through the center of the city have been replaced in recent years using a rapid bridge replacement procedure. New bridge sections (one for the east bound lanes and one for the west bound lanes) are built off site. Traffic needs to be rerouted for less than 72 hours on a long weekend in the summer to enable demolition of the old bridge sections and installation of the new bridge sections. This has worked well and is far more preferable to having many months of traffic disruption.
Alfred Tennyson wrote:We are not now that strength which in old days
Moved earth and heaven, that which we are, we are;
One equal temper of heroic hearts,
Made weak by time and fate, but strong in will
To strive, to seek, to find, and not to yield.
vtsnowedin wrote: One of the last state jobs I worked on was a 20 million dollar upgrade to an exit with 60,000 vehicles a day and five bridges. We built widened lanes and temporary bridge widening s to provide a new lane before any old lane was closed. Much of the work on the commercial street under the interstate was done at night so all traffic was free flowing or at least as much as it would be under normal traffic light control. The costs of the temporary lanes was some two million dollars. There is more then one way to skin a cat.
Because the bridge's central tower and suspension cables were not yet installed, the Miami Herald notes that any cables being tightened were likely wires that ran through the span that fell on Thursday.
I suspect that is just a reporter misunderstanding what they are being told by a politician that doesn't know what he is talking about.Newfie wrote:Because the bridge's central tower and suspension cables were not yet installed, the Miami Herald notes that any cables being tightened were likely wires that ran through the span that fell on Thursday.
https://www.npr.org/sections/thetwo-way ... ami-bridge
I find that an incredible statement if true. Who would put up a suspension bridge BEFORE installing the cables? Incredible.
Newfie wrote:And another thing, why would you “stress test” an unstayed suspension bridge?
What the heck do they mean by “stress test”? I think of loading it with weight and measuring deflection. But that makes zero sense to me at this point?
Not much makes any sense.
I have to believe there is something substantially wrong with the reporting. Even civil engineers aren’t that stupid.
Newfie PE ( Electrical) Ret
Engineer on Fla. bridge project called state to report crack days before collapse
The Florida Department of Transportation
vtsnowedin wrote:Newfie wrote:And another thing, why would you “stress test” an unstayed suspension bridge?
What the heck do they mean by “stress test”? I think of loading it with weight and measuring deflection. But that makes zero sense to me at this point?
Not much makes any sense.
I have to believe there is something substantially wrong with the reporting. Even civil engineers aren’t that stupid.
Newfie PE ( Electrical) Ret
Again they are just in the state of confusion.
As you jack a cable to put tension on the structure there is a gauge on the jack and the final tension is recorded but I would not call that a test. They were probably going from one cable to another to get them all even but why that would cause this failure is beyond what I know now.
Return to Open Topic Discussion
Users browsing this forum: No registered users and 4 guests